The sequence at a glance
Once the stop checks are clear, the work follows an order that builds from the outside of the problem inward. You fix anything that is pumping moisture into the attic, you close the largest openings, you close the countless small ones, you protect the ventilation path, and only then do you add depth. The table below is the sequence to hold a contractor to, or to follow yourself in the parts that are safe to do.
Fixing what vents into the attic
Bathroom fans and dryers are the most common surprise in a Canadian attic. A flexible duct that has slipped off its roof cap, or was never connected to one, turns a humid shower into a direct delivery of moisture to your roof boards. The Part 9 rules that govern houses across Canada are straightforward here: exhaust ducts shall discharge to the outdoors, and dryer exhaust has to discharge directly outdoors through its own smooth, accessible duct.
Where the duct ends matters as well. The 2020 edition of the National Building Code of Canada added a rule, quoted in Alberta's code variance on exhaust clearances, that moisture-laden exhaust outlets sit at least 1,800 mm from vented soffits, or that the soffit next to the outlet is blocked. A fan duct pushed out through the soffit vent it sits beside simply sends the damp air back into the attic intake. Fix these before anything gets buried, because once there is a foot of new insulation on top, nobody is going to go looking for them.
Closing the chimney and flue gaps safely
The gap around a chimney is often the single largest hole in an attic floor, and it is also the one place where the wrong material creates a fire risk. Federal guidance asks you to keep insulation 75 mm (3 in.) from the face of a masonry chimney, with a non-combustible barrier rising at least 75 mm above the top of the insulation, and to follow the manufacturer's clearance for factory-built metal chimneys, which also need a non-flammable radiation shield.
The seal itself is made with metal, not foam. A good contractor cuts sheet metal to span the gap, fastens it to the framing, and seals the edges with a non-combustible or high-temperature sealant rated for the job. ENERGY STAR describes the same approach using lightweight aluminum flashing and heat-resistant caulk, with a caution that furnace flues can be very hot. Ordinary expanding foam, regular latex caulk and fibreglass stuffed into the gap do not belong anywhere near a chimney or a B-vent.
Big holes first, then the small ones
With the chimney handled, the rest of the sealing follows a simple rule of thumb: cover the big openings, then chase the small ones. Big openings include the tops of interior walls that were never capped, plumbing chases, and the hollow boxes over kitchen cabinets and bulkheads that open straight into the attic. These are covered with rigid board or panel material, then sealed around every edge so air cannot slip past.
The small openings are where the patience comes in. Natural Resources Canada's attic guidance describes pulling back the existing insulation to locate and caulk cracks along interior walls, checking that exterior wall cavities are blocked from the attic, and sealing a plumbing stack with a flexible gasket or a polyethylene sleeve sealed to a plywood collar. The same guidance covers wires and ceiling fixtures that pass through the attic floor, and ducts, whose joints and ceiling penetrations are sealed with foil tape or mastic. Around anything that gets warm, from chimneys to fan motors to light fixtures, the sealant has to be non-combustible, and silicone or polysulphide products are the usual choices.
Pot lights and the hatch
Older recessed lights deserve their own step, because they are both leaks and heat sources. Federal guidance notes that standard recessed lights are difficult to air seal and can become a fire hazard if covered with insulation. The fix depends on the fixture's rating. The U.S. Department of Energy's Building America Solution Center explains that insulation-contact airtight fixtures are built with fewer holes and gaskets, so insulation can go over and around them, while cans without that rating need a protective cover that keeps insulation off the fixture and is sealed to the ceiling below. If you are unsure what you have, an electrician can read the label on the housing.
The attic hatch comes last among the openings, and it is the one most often forgotten after a top-up. It should close against weatherstripping, latch or weigh down firmly, carry rigid insulation on its top face, and have a dam built around the opening so the new loose-fill does not spill over the edge when someone climbs up next spring.
Baffles, then depth
Only now does the ventilation path get its protection. Part 9 of the building code, in the long-standing wording used by provinces such as British Columbia and Ontario, requires at least 63 mm of space between the top of the insulation and the underside of the roof sheathing, and where preformed baffles are used at the eaves they must leave an air space of at least 25 mm and rise at least 50 mm above the top of the insulation. The same section sets attic vent area at no less than 1/300 of the insulated ceiling area, split between openings near the bottom and the top of the roof. Codes are updated every few years, so ask your municipality or contractor to confirm the edition in force where you live.
In practice, baffles go into every rafter bay that sits above a vented soffit, so the new depth cannot smother the air coming in at the eaves. Then the blower door test is run if you are working with an energy advisor, and only after that does the insulation hose come up the ladder. For a deeper look at how intake and exhaust vents work together in a cold climate, our hub on attic ventilation in cold climates walks through the whole system.