Construction Holdback Explained: What Canadian Lien Law Holds Back, for How Long, and Who Releases It
How the 10% You Keep Back Protects You, Province by Province, With a Worked Kitchen Renovation
By
Published: October 14, 2026
Fact-checked · , including Government of Ontario, Government of British Columbia & Government of Alberta
Credit: Homeowner.ca
Key Takeaways
•Every province except Quebec asks you to hold back part of each renovation payment. The share is 10% in most provinces, 7.5% in Manitoba and 15% to 20% in Prince Edward Island.
•The holdback stays with you until the lien window closes, which runs from completion or substantial performance. That's anywhere from 30 days in Newfoundland and Labrador to 60 days in Ontario and most of the Prairies.
•Release it only after the window has closed and a title search shows no lien. Kept properly, the holdback caps what an unpaid supplier can recover from you. If you skip it, you can end up paying that amount twice.
Picture the moment your renovator hands over the invoice for the first draw. The old cabinets are gone, the new plumbing is roughed in, and you're ready to pay the whole thing because the work is clearly there. Most homeowners never hear that the law in their province expects them to keep a slice of that payment back. Contractors who know the rule don't always bring it up, and it can feel a little awkward to raise it yourself.
Here's the reframe that makes it easier. Holding back isn't a sign of distrust, and it isn't a penalty aimed at your contractor. It's the mechanism provincial lien law uses to protect you. Behind your contractor stand a cabinet shop, a plumber, a lumber yard and a countertop fabricator, and any of them can register a lien on your home's title if the contractor doesn't pay them. The holdback is the pot of money the law sets aside for that possibility. Keep it properly and your exposure has a ceiling. Skip it and you may pay the same money twice.
This guide walks through what the holdback is, how much each province requires, when the clock starts and stops, and who releases the money at the end. It includes a province-by-province table and a dated, draw-by-draw walk-through of a $60,000 Ontario kitchen. Quebec, which handles all of this differently, gets its own section. None of this is legal advice. It's a clear picture of what the statutes ask of you, so you know when a quick call to a lawyer is worth making.
What a construction holdback actually is
A reserve built into every payment you make
In the common-law provinces, a construction holdback is a percentage you keep back from each payment to your contractor while the work is under way. Ontario's version is typical. Under the Ontario Construction Act, each payer on a contract where a lien may arise must retain 10 per cent of the price of the services or materials as they are actually supplied, until any liens that could be claimed against that money have expired or been dealt with.
Two details matter more than they first appear. The first is timing: the holdback builds up draw by draw as work is supplied. It isn't one lump you set aside on the final day. The second is the wording "each payer". The same duty runs down the chain, so your general contractor is expected to hold back from the subcontractors, and they hold back from theirs. Every level keeps a little in reserve for the people below it.
Why it protects you, not just the trades
It's easy to read the holdback as a rule that exists only to help unpaid trades, but look at what it does for the homeowner. Suppose your contractor collects your payments and then fails to pay the cabinet supplier. That supplier never had a contract with you, yet in every common-law province it can register a lien against your property. Without a limit, you could be asked to pay for cabinets you've already paid for once.
The holdback is that limit. British Columbia says it most plainly: under the BC Builders Lien Act, the most that all lien claimants under the same contractor can recover is the greater of what you still owe that contractor and the holdback you were required to keep. Ontario and Saskatchewan get to the same place by making the owner personally liable to lien claimants for the holdback the owner was required to retain. The Atlantic statutes add that a lien can't make the owner liable for more than the sum payable to the contractor.
So the math works in your favour when you follow the rule. If you've kept $6,000 back and an unpaid supplier claims $9,000, your exposure is measured by that $6,000 fund, not by the size of the supplier's claim.
What happens if you don't hold back? Your liability is still measured by the holdback you should have kept. As MLT Aikins explains, a payer who didn't maintain the holdback or paid it out improperly may be forced to pay those amounts again. The ceiling hasn't gone anywhere. You've just already spent the money that was supposed to sit under it.
Liens are one of those homeowner obligations that surprise people because they show up on title rather than in your mailbox.
In the common-law provinces, a construction holdback is a percentage you keep back from each payment to your contractor while the work is under way. Ontario's version is typical. Under the Ontario Construction Act, each payer on a contract where a lien may arise must retain 10 per cent of the price of the services or materials as they are actually supplied, until any liens that could be claimed against that money have expired or been dealt with.
Two details matter more than they first appear. The first is timing: the holdback builds up draw by draw as work is supplied. It isn't one lump you set aside on the final day. The second is the wording "each payer". The same duty runs down the chain, so your general contractor is expected to hold back from the subcontractors, and they hold back from theirs. Every level keeps a little in reserve for the people below it.
Why it protects you, not just the trades
It's easy to read the holdback as a rule that exists only to help unpaid trades, but look at what it does for the homeowner. Suppose your contractor collects your payments and then fails to pay the cabinet supplier. That supplier never had a contract with you, yet in every common-law province it can register a lien against your property. Without a limit, you could be asked to pay for cabinets you've already paid for once.
The holdback is that limit. British Columbia says it most plainly: under the BC Builders Lien Act, the most that all lien claimants under the same contractor can recover is the greater of what you still owe that contractor and the holdback you were required to keep. Ontario and Saskatchewan get to the same place by making the owner personally liable to lien claimants for the holdback the owner was required to retain. The Atlantic statutes add that a lien can't make the owner liable for more than the sum payable to the contractor.
So the math works in your favour when you follow the rule. If you've kept $6,000 back and an unpaid supplier claims $9,000, your exposure is measured by that $6,000 fund, not by the size of the supplier's claim.
What happens if you don't hold back? Your liability is still measured by the holdback you should have kept. As MLT Aikins explains, a payer who didn't maintain the holdback or paid it out improperly may be forced to pay those amounts again. The ceiling hasn't gone anywhere. You've just already spent the money that was supposed to sit under it.
Liens are one of those homeowner obligations that surprise people because they show up on title rather than in your mailbox.
There's no national holdback rule. Each province writes its own, and the differences are big enough to change your renovation plan. The table below comes from each province's current statute or government guidance as of September 2026. Where we couldn't confirm a detail from a primary source, the cell says so rather than guessing.
10 rows · 8 columnsTap a header to sort
Ontario
10% of each payment
Completion, or a published certificate of substantial performance if earlier
60 days to preserve, then 90 to perfect
Within 14 days after the 60-day window closes, if title is clear
28 days (7 days to object to an invoice)
No
Construction Act ss. 22, 23, 31, 36
British Columbia
10% of the greater of work value or payments made
Certificate of completion, or completion/abandonment
45 days
After the holdback period ends, 55 days from the trigger
Enacted November 2025, not yet in force
Yes, unless the contract is under $100,000
Builders Lien Act ss. 4, 5, 8, 20, 34
Alberta
10% of each payment
Certificate of substantial performance, or completion
60 days (90 for concrete)
After at least 60 days, if no lien is registered
28 days
No
Prompt Payment and Construction Lien Act s. 18
Saskatchewan
10% of the greater of work value or payments made
Certificate of substantial performance
40 days
40 clear days after the certificate is given
28 days
Not confirmed
Builders' Lien Act ss. 34, 37, 43
Manitoba
7.5% of each payment
Substantial performance or abandonment
60 days (contracts from April 1, 2025; 40 before)
At least 60 days after the trigger
28 days
Not confirmed
Builders' Liens Act ss. 24, 43
Nova Scotia
10% of work value
Substantial performance (ready for use, 2.5% or less left)
60 days after completion or abandonment
60 days after substantial performance; interest after 65
Enacted 2019, not yet in force
Not confirmed
Builders' Lien Act
New Brunswick
10%
Certificate or declaration of substantial performance
60 days
60 days after the certificate or declaration
Enacted 2023, not yet in force
No
Construction Remedies Act
Prince Edward Island
20%, or 15% if the work exceeds $15,000
Completion or abandonment
60 days
60 days after completion or abandonment
Not confirmed
Not confirmed
Mechanics' Lien Act s. 14
Newfoundland and Labrador
10%
Completion or abandonment
30 days to register; the lien ends at 90 days unless an action is started
30 days after completion or abandonment
Not confirmed
Not confirmed
Mechanics' Lien Act ss. 12, 22, 24
Quebec
No statutory holdback
End of work
30 days to register a legal hypothec; 6 months to act on it
See the Quebec section below
Public contracts only
Not applicable
Civil Code arts. 2726–2728
What stands out once you read across the rows
Read the table as a whole and a few surprises come through. Manitoba is the only province below 10%, and it recently lengthened its clock. The province's Builders' Liens Amendment Act (Prompt Payment) extended the lien deadlines from 40 to 60 days for contracts signed on or after April 1, 2025. The province's own consumer page on home improvements still describes a 7.5% holdback kept for 40 days. That's accurate only for older contracts, so if you signed with a Manitoba renovator this year, count 60 days.
Prince Edward Island sits at the other end. Its Mechanics' Lien Act has an owner retain 20% of the value of work and materials for 60 days after completion or abandonment, dropping to 15% once the value of the work passes $15,000. On a small bathroom refresh, that's a noticeably larger share to keep back than anywhere else in the country.
Newfoundland and Labrador moves fastest. Under the province's Mechanics' Lien Act, the 10% holdback is kept for 30 days after completion or abandonment, liens must be registered within the same 30 days, and a registered lien stops existing after 90 days unless the claimant starts a court action.
New Brunswick changed its rules more quietly. The Construction Remedies Act replaced the old Mechanics' Lien Act in November 2021. It cut the holdback from 15% to 10% and removed the requirement to keep it in a separate trust account, so older Maritime guidance quoting 15% for New Brunswick is out of date.
In Alberta, the 2022 reforms stretched both the holdback period and the lien window from 45 to 60 days. As McCarthy Tétrault describes it, the owner keeps 10% of each payment for at least 60 days after a certificate of substantial performance, or after completion if no certificate is issued, and doesn't need a separate account for it.
British Columbia is the province most likely to catch a homeowner off guard on paperwork, because owner holdbacks are supposed to go into a holdback account once a contract reaches $100,000. The province's new prompt-payment law is also still waiting in the wings. The Province of British Columbia confirms the Construction Prompt Payment Act received Royal Assent on November 27, 2025, but isn't in force yet, so BC homeowners don't face a statutory 28-day payment clock today.
The provincial table
There's no national holdback rule. Each province writes its own, and the differences are big enough to change your renovation plan. The table below comes from each province's current statute or government guidance as of September 2026. Where we couldn't confirm a detail from a primary source, the cell says so rather than guessing.
10 rows · 8 columnsTap a header to sort
Ontario
10% of each payment
Completion, or a published certificate of substantial performance if earlier
60 days to preserve, then 90 to perfect
Within 14 days after the 60-day window closes, if title is clear
28 days (7 days to object to an invoice)
No
Construction Act ss. 22, 23, 31, 36
British Columbia
10% of the greater of work value or payments made
Certificate of completion, or completion/abandonment
45 days
After the holdback period ends, 55 days from the trigger
Enacted November 2025, not yet in force
Yes, unless the contract is under $100,000
Builders Lien Act ss. 4, 5, 8, 20, 34
Alberta
10% of each payment
Certificate of substantial performance, or completion
60 days (90 for concrete)
After at least 60 days, if no lien is registered
28 days
No
Prompt Payment and Construction Lien Act s. 18
Saskatchewan
10% of the greater of work value or payments made
Certificate of substantial performance
40 days
40 clear days after the certificate is given
28 days
Not confirmed
Builders' Lien Act ss. 34, 37, 43
Manitoba
7.5% of each payment
Substantial performance or abandonment
60 days (contracts from April 1, 2025; 40 before)
At least 60 days after the trigger
28 days
Not confirmed
Builders' Liens Act ss. 24, 43
Nova Scotia
10% of work value
Substantial performance (ready for use, 2.5% or less left)
60 days after completion or abandonment
60 days after substantial performance; interest after 65
Enacted 2019, not yet in force
Not confirmed
Builders' Lien Act
New Brunswick
10%
Certificate or declaration of substantial performance
60 days
60 days after the certificate or declaration
Enacted 2023, not yet in force
No
Construction Remedies Act
Prince Edward Island
20%, or 15% if the work exceeds $15,000
Completion or abandonment
60 days
60 days after completion or abandonment
Not confirmed
Not confirmed
Mechanics' Lien Act s. 14
Newfoundland and Labrador
10%
Completion or abandonment
30 days to register; the lien ends at 90 days unless an action is started
30 days after completion or abandonment
Not confirmed
Not confirmed
Mechanics' Lien Act ss. 12, 22, 24
Quebec
No statutory holdback
End of work
30 days to register a legal hypothec; 6 months to act on it
See the Quebec section below
Public contracts only
Not applicable
Civil Code arts. 2726–2728
What stands out once you read across the rows
Read the table as a whole and a few surprises come through. Manitoba is the only province below 10%, and it recently lengthened its clock. The province's Builders' Liens Amendment Act (Prompt Payment) extended the lien deadlines from 40 to 60 days for contracts signed on or after April 1, 2025. The province's own consumer page on home improvements still describes a 7.5% holdback kept for 40 days. That's accurate only for older contracts, so if you signed with a Manitoba renovator this year, count 60 days.
Prince Edward Island sits at the other end. Its Mechanics' Lien Act has an owner retain 20% of the value of work and materials for 60 days after completion or abandonment, dropping to 15% once the value of the work passes $15,000. On a small bathroom refresh, that's a noticeably larger share to keep back than anywhere else in the country.
Newfoundland and Labrador moves fastest. Under the province's Mechanics' Lien Act, the 10% holdback is kept for 30 days after completion or abandonment, liens must be registered within the same 30 days, and a registered lien stops existing after 90 days unless the claimant starts a court action.
New Brunswick changed its rules more quietly. The Construction Remedies Act replaced the old Mechanics' Lien Act in November 2021. It cut the holdback from 15% to 10% and removed the requirement to keep it in a separate trust account, so older Maritime guidance quoting 15% for New Brunswick is out of date.
In Alberta, the 2022 reforms stretched both the holdback period and the lien window from 45 to 60 days. As McCarthy Tétrault describes it, the owner keeps 10% of each payment for at least 60 days after a certificate of substantial performance, or after completion if no certificate is issued, and doesn't need a separate account for it.
British Columbia is the province most likely to catch a homeowner off guard on paperwork, because owner holdbacks are supposed to go into a holdback account once a contract reaches $100,000. The province's new prompt-payment law is also still waiting in the wings. The Province of British Columbia confirms the Construction Prompt Payment Act received Royal Assent on November 27, 2025, but isn't in force yet, so BC homeowners don't face a statutory 28-day payment clock today.
Note
Ontario's Construction Act, and Alberta's, Saskatchewan's and Manitoba's lien statutes, now pair the holdback with a prompt-payment clock. Once your contractor gives you a proper invoice, you generally have 28 days to pay it, or you must give a formal notice explaining what you're withholding and why. The holdback is still deducted from each payment inside that system. It doesn't replace it.
How long you hold it: the clock and what starts it
Substantial performance, completion, and why the difference matters
Every holdback rule has two moving parts: the event that starts the clock, and the number of days that follow. The number is easy to look up. The event is where homeowners tend to get tangled.
Most provinces key the clock to "substantial performance". Put simply, that's the point where the job is ready to use even though a few small items are still outstanding. Nova Scotia gives the most concrete test. Under its Builders' Lien Act, a contract is substantially performed when the work is ready for use or is being used as intended, and what's left can be finished or corrected for no more than 2.5% of the contract price. Nova Scotia then asks the owner to keep the 10% holdback for 60 days after that point and adds interest if it isn't paid within 65 days.
On a big commercial project, someone formally certifies substantial performance and publishes the certificate, and that publication starts the clock. On a household renovation this usually doesn't happen. In Ontario, when no certificate is published, the 60-day lien window runs from the date the contract is completed, abandoned or terminated. For a kitchen or bathroom, the practical start of your clock is usually the day the last piece of contracted work is done.
The two clocks that run in Ontario
Ontario adds a second layer that's worth understanding. After the 60-day window to preserve a lien, a claimant who did register has another 90 days to "perfect" it by starting a court action. The team at Nihang Law sums it up as 60 days to preserve and then perfect, up to 150 days in total. You don't have to wait the full 150 days to release your holdback. The release turns on the first window closing with a clear title. The longer tail matters only if a lien actually lands.
In British Columbia the two clocks are deliberately offset. Liens must be filed within 45 days, but the holdback period runs for 55 days, according to the British Columbia Law Institute. Those extra ten days give you time to pull a title search after the filing window has shut and before any money moves.
Warning
Paying the last draw is not the same as the job being complete. If your contractor comes back weeks later to finish contracted work, such as installing a backordered range hood, the completion date, and your clock with it, may shift later. Keep a dated record of when the last contracted item was actually finished.
A worked example: a $60,000 Ontario kitchen, draw by draw
The draws, and what you keep back from each one
To see how this plays out, follow a $60,000 kitchen renovation in Ontario, paid in four equal draws as work is supplied. The contract builds the holdback into the payment schedule from day one. No certificate of substantial performance is published, because this is a household job. To keep the arithmetic clean, the figures leave HST out.
By the time the last cabinet door is hung, you've paid $54,000 and quietly kept $6,000 in reserve. Each invoice also opens a short window worth knowing about. Since January 1, 2026, an Ontario invoice is deemed "proper" unless you point out its deficiencies in writing within 7 days. If a draw invoice is missing information you need, say so that week.
The calendar after the last nail
Once the fourth draw's work is done on Friday, November 27, 2026, the contract is complete and the 60-day clock starts. Here's how the weeks unfold:
Friday, November 27, 2026 (day 0): The contract is completed and the lien window opens.
Monday, January 11, 2027 (day 45): In our example, this is when trouble arrives (see below).
Tuesday, January 26, 2027 (day 60): The 60-day preservation window closes.
Wednesday, January 27, 2027: You run a title search to confirm nothing is registered.
By Tuesday, February 9, 2027: If title is clear, the $6,000 holdback goes to your contractor. The deadline is 14 days after the window closes.
That last date is a real obligation. After the January 2026 amendments, Cassels notes that the owner must pay the remaining holdback to the contractor within 14 days after the lien-preservation period has expired, or after any preserved liens are satisfied, discharged or otherwise provided for. Holding on to it "just in case" past that point isn't an option the statute gives you.
What happens when a supplier registers a lien on day 45
Now for the scenario the holdback exists for. On January 11, 2027, the cabinet supplier registers a $9,000 lien on your home's title because your contractor never paid for the boxes and doors. You had no contract with the supplier, and you paid your contractor every draw on time.
Here's where the $6,000 earns its keep. Under Ontario's Construction Act, your personal liability to valid lien claimants is tied to the holdback you were required to retain. The supplier's claim is $9,000, but the fund you're answerable for is the $6,000 you kept back. You don't release that money to the contractor while the lien sits on title, and this is the moment to call a construction lawyer, before any more money changes hands, so the lien is dealt with through the process the Act sets out.
Now imagine a neighbour who did the same renovation and paid all $60,000 as each invoice arrived. Their liability is still measured by the $6,000 they were supposed to keep back, but that money is already in the contractor's account. To clear the supplier's claim against their home, they may have to find up to $6,000 more out of pocket. It's the same kitchen and the same supplier, and one homeowner pays twice while the other doesn't.
Some homeowners finance a kitchen like this through home equity, and the draw schedule matters there too.
If you're weighing how to fund a renovation, our guide to HELOCs explained covers how draws from a line of credit line up with progress payments.
The draws, and what you keep back from each one
To see how this plays out, follow a $60,000 kitchen renovation in Ontario, paid in four equal draws as work is supplied. The contract builds the holdback into the payment schedule from day one. No certificate of substantial performance is published, because this is a household job. To keep the arithmetic clean, the figures leave HST out.
By the time the last cabinet door is hung, you've paid $54,000 and quietly kept $6,000 in reserve. Each invoice also opens a short window worth knowing about. Since January 1, 2026, an Ontario invoice is deemed "proper" unless you point out its deficiencies in writing within 7 days. If a draw invoice is missing information you need, say so that week.
The calendar after the last nail
Once the fourth draw's work is done on Friday, November 27, 2026, the contract is complete and the 60-day clock starts. Here's how the weeks unfold:
Friday, November 27, 2026 (day 0): The contract is completed and the lien window opens.
Monday, January 11, 2027 (day 45): In our example, this is when trouble arrives (see below).
Tuesday, January 26, 2027 (day 60): The 60-day preservation window closes.
Wednesday, January 27, 2027: You run a title search to confirm nothing is registered.
By Tuesday, February 9, 2027: If title is clear, the $6,000 holdback goes to your contractor. The deadline is 14 days after the window closes.
That last date is a real obligation. After the January 2026 amendments, Cassels notes that the owner must pay the remaining holdback to the contractor within 14 days after the lien-preservation period has expired, or after any preserved liens are satisfied, discharged or otherwise provided for. Holding on to it "just in case" past that point isn't an option the statute gives you.
What happens when a supplier registers a lien on day 45
Now for the scenario the holdback exists for. On January 11, 2027, the cabinet supplier registers a $9,000 lien on your home's title because your contractor never paid for the boxes and doors. You had no contract with the supplier, and you paid your contractor every draw on time.
Here's where the $6,000 earns its keep. Under Ontario's Construction Act, your personal liability to valid lien claimants is tied to the holdback you were required to retain. The supplier's claim is $9,000, but the fund you're answerable for is the $6,000 you kept back. You don't release that money to the contractor while the lien sits on title, and this is the moment to call a construction lawyer, before any more money changes hands, so the lien is dealt with through the process the Act sets out.
Now imagine a neighbour who did the same renovation and paid all $60,000 as each invoice arrived. Their liability is still measured by the $6,000 they were supposed to keep back, but that money is already in the contractor's account. To clear the supplier's claim against their home, they may have to find up to $6,000 more out of pocket. It's the same kitchen and the same supplier, and one homeowner pays twice while the other doesn't.
Some homeowners finance a kitchen like this through home equity, and the draw schedule matters there too.
If you're weighing how to fund a renovation, our guide to HELOCs explained covers how draws from a line of credit line up with progress payments.
Who releases the holdback, and how to do it safely
You release it, once title is clear
In every common-law province, the person who kept the holdback releases it, and on a home renovation that's you. The release is a simple payment to your contractor. The care goes into the day before, when you confirm that no lien has landed on your title while you were waiting out the clock.
In Ontario, checking is straightforward. According to the OnLand Help Centre, you perform a property search on OnLand and purchase the Parcel Register for your home. Registered liens show up there alongside your mortgage.
In British Columbia, the Land Title and Survey Authority explains that a title lists the charges, liens and interests registered against the property. You'll need your nine-digit Parcel Identifier rather than your street address, and there's a fee to order the title. You can use an LTSA Explorer account, a mailed request for a State of Title Certificate, or a professional who orders it for you.
In Alberta, the province's land titles guidance confirms that current titles show registered builders' liens, and title searches are available through SPIN2 or any registry agent. In the other provinces, the land registry or a local lawyer can run the same check. It's a small cost next to the amount you're about to release.
Tip
Run the title search the day after the lien window closes, not a week before. A lien registered on the last permitted day won't show up in an earlier search, and that last-day registration is exactly the one you're guarding against.
In Ontario, the holdback is no longer your deficiency fund
Many homeowners treat the holdback as leverage: keep the 10% until the contractor comes back to fix the sticky drawer or the chipped tile. In Ontario, that approach largely stopped working on January 1, 2026. As Loopstra Nixon explains, owners lost the option of giving a notice of non-payment of holdback. Holdback money can now be used against a contractor's claims only in the narrow situation where the contract has been abandoned or terminated and the lien period has expired.
So if you want a reserve for deficiencies, build one into your contract as its own line: a clearly defined amount, tied to a written deficiency list, released when those items are done. Keep it separate from the statutory holdback, which has its own job and its own release date. The same January 2026 amendments also made annual holdback release mandatory on Ontario contracts that run longer than a year. That's worth knowing if your project is a large addition or a whole-home renovation that crosses an anniversary.
Contract wording has been doing a lot of work for Ontario homeowners this fall.
Our earlier piece on renovation contracts signed before September 8 covers what your province says about mid-job price increases, which pairs naturally with a well-drafted payment schedule.
In Ontario, the holdback is no longer your deficiency fund
Many homeowners treat the holdback as leverage: keep the 10% until the contractor comes back to fix the sticky drawer or the chipped tile. In Ontario, that approach largely stopped working on January 1, 2026. As Loopstra Nixon explains, owners lost the option of giving a notice of non-payment of holdback. Holdback money can now be used against a contractor's claims only in the narrow situation where the contract has been abandoned or terminated and the lien period has expired.
So if you want a reserve for deficiencies, build one into your contract as its own line: a clearly defined amount, tied to a written deficiency list, released when those items are done. Keep it separate from the statutory holdback, which has its own job and its own release date. The same January 2026 amendments also made annual holdback release mandatory on Ontario contracts that run longer than a year. That's worth knowing if your project is a large addition or a whole-home renovation that crosses an anniversary.
Contract wording has been doing a lot of work for Ontario homeowners this fall.
Our earlier piece on renovation contracts signed before September 8 covers what your province says about mid-job price increases, which pairs naturally with a well-drafted payment schedule.
Quebec works differently: the legal hypothec and dénonciation
No holdback, but a clock you still need to watch
If you're renovating in Quebec, the holdback table above doesn't describe your situation, and that's by design. Quebec's civil law has no statutory holdback. Instead, the people who work on or supply materials for your renovation hold a legal construction hypothec, a security right against your property for the value they added to it.
The timing is what homeowners need to keep in mind. As the Association des consommateurs pour la qualité dans la construction explains, the builder must register the hypothec at the Registre foncier du Québec within 30 days after the end of the work. To keep it alive, they must then register a prior notice or publish an action against the owner within six months after the end of the work. The hypothec also requires that the work actually added value to the building.
Dénonciation is your early-warning system
Quebec gives homeowners a different tool in place of a holdback: knowing who's on your job. A subcontractor or supplier who didn't contract with you directly must dénoncer their contract to you in writing, giving the approximate value and their potential right to a hypothec, before doing the work. When a dénonciation arrives, you know exactly who could later make a claim against your home, and you can make sure they're paid, for example by asking for proof of payment or paying jointly, before you settle the final invoice.
Quebec clients also have a separate right to hold back a sum sufficient to correct defects or poor workmanship. That comes from the law of contracts rather than lien law, and it's worth knowing when the final walkthrough turns up problems.
No holdback, but a clock you still need to watch
If you're renovating in Quebec, the holdback table above doesn't describe your situation, and that's by design. Quebec's civil law has no statutory holdback. Instead, the people who work on or supply materials for your renovation hold a legal construction hypothec, a security right against your property for the value they added to it.
The timing is what homeowners need to keep in mind. As the Association des consommateurs pour la qualité dans la construction explains, the builder must register the hypothec at the Registre foncier du Québec within 30 days after the end of the work. To keep it alive, they must then register a prior notice or publish an action against the owner within six months after the end of the work. The hypothec also requires that the work actually added value to the building.
Dénonciation is your early-warning system
Quebec gives homeowners a different tool in place of a holdback: knowing who's on your job. A subcontractor or supplier who didn't contract with you directly must dénoncer their contract to you in writing, giving the approximate value and their potential right to a hypothec, before doing the work. When a dénonciation arrives, you know exactly who could later make a claim against your home, and you can make sure they're paid, for example by asking for proof of payment or paying jointly, before you settle the final invoice.
Quebec clients also have a separate right to hold back a sum sufficient to correct defects or poor workmanship. That comes from the law of contracts rather than lien law, and it's worth knowing when the final walkthrough turns up problems.
Setting it up before the first draw
Put the holdback in the contract, not in a conversation
The easiest time to handle the holdback is before any money moves. Alberta's consumer guidance on hiring a contractor recommends that your contract include a clearly itemized payment schedule that shows any holdback provisions. That's sound advice anywhere in Canada. When the percentage, the draw stages and the expected release date are written into the schedule, nobody is surprised when draw one comes in 10% lighter than the invoice.
A few practical details make the release smoother later:
Name the statute and the percentage in the payment schedule, so the holdback reads as a legal requirement rather than a negotiating position.
Tie each draw to a stage of work you can see and photograph, since the holdback is calculated on work as it's actually supplied.
Agree on how completion will be recorded, such as a signed note or an email confirming the last contracted item is finished, so both of you are counting from the same day.
Ask your contractor for a list of major subcontractors and suppliers. It makes a later lien far easier to understand, and in Quebec it tells you whose dénonciation to expect.
When a lender is advancing the money
If your renovation is funded by a construction mortgage or staged advances, your lender may handle the holdback for you. In British Columbia, for example, the Builders Lien Act allows a savings institution that disburses the mortgage money to retain the holdback on the owner's behalf. Ask your lender at the outset whether it holds back from each advance, so you aren't holding back twice or not at all.
A tariff surprise on cabinets or vanities is one more reason to keep your payment records tidy while the kitchen comes together.
Put the holdback in the contract, not in a conversation
The easiest time to handle the holdback is before any money moves. Alberta's consumer guidance on hiring a contractor recommends that your contract include a clearly itemized payment schedule that shows any holdback provisions. That's sound advice anywhere in Canada. When the percentage, the draw stages and the expected release date are written into the schedule, nobody is surprised when draw one comes in 10% lighter than the invoice.
A few practical details make the release smoother later:
Name the statute and the percentage in the payment schedule, so the holdback reads as a legal requirement rather than a negotiating position.
Tie each draw to a stage of work you can see and photograph, since the holdback is calculated on work as it's actually supplied.
Agree on how completion will be recorded, such as a signed note or an email confirming the last contracted item is finished, so both of you are counting from the same day.
Ask your contractor for a list of major subcontractors and suppliers. It makes a later lien far easier to understand, and in Quebec it tells you whose dénonciation to expect.
When a lender is advancing the money
If your renovation is funded by a construction mortgage or staged advances, your lender may handle the holdback for you. In British Columbia, for example, the Builders Lien Act allows a savings institution that disburses the mortgage money to retain the holdback on the owner's behalf. Ask your lender at the outset whether it holds back from each advance, so you aren't holding back twice or not at all.
A tariff surprise on cabinets or vanities is one more reason to keep your payment records tidy while the kitchen comes together.
Angela Nightingale is the Senior Editor at Homeowner.ca with two decades of experience in digital publishing and content strategy. She has owned two homes, taken on her share of DIY projects, and learned what most guides fail to mention. She writes from the belief that the best home guidance comes from people who have lived through the decisions — and her goal is always to leave readers feeling confident, not overwhelmed.
In most provinces, yes. The duty applies to any contract where a lien can arise, and household renovations are included. British Columbia's $100,000 threshold only decides whether the holdback has to sit in a separate account, not whether you keep it. Ontario has no size-based exemption.
It's calculated on work as it's supplied, so in practice you deduct the percentage from each draw. On a $60,000 Ontario job paid in four $15,000 draws, that's $1,500 per draw and $6,000 by the end.
On most household jobs no certificate of substantial performance is published, so the window usually runs from the date the contract is completed. Keep a dated record of when the last contracted item was finished.
No. The statutes don't carve out homeowners, and the protection runs mainly to you. If you pay everything out and an unpaid supplier registers a lien, you can still be responsible for the amount you should have held back.
In Ontario, not any more. Since January 1, 2026, owners can't use a notice of non-payment of holdback, and the holdback must be released within 14 days after the lien window closes if title is clear. Set up a separate deficiency amount in your contract instead.
Order a current title or parcel register from your provincial land registry after the lien window closes: OnLand in Ontario, the LTSA in British Columbia, or SPIN2 or a registry agent in Alberta. A lawyer or registry agent can do it for you anywhere in Canada.
Yes. The prompt-payment part of the Construction Act has no residential carve-out, so a proper invoice from your contractor generally has to be paid within 28 days, or you must give a notice of non-payment within 14 days. The holdback is still deducted from each payment.
Don't release the holdback to your contractor, and don't make any further payments until you've spoken with a construction lawyer. The holdback you kept is the fund the statute looks to, and a lawyer can explain how the lien gets resolved under your province's Act.
It depends on when you signed. Contracts entered into on or after April 1, 2025, fall under the amended rules with 60-day lien deadlines. Older contracts keep the previous 40-day windows, which is what the province's consumer page still describes.
Quebec has no statutory holdback. The protection works through the legal construction hypothec and written dénonciations from subcontractors and suppliers. Quebec clients can, however, keep back a sum sufficient to correct defects under the rules on contracts.