The draws, and what you keep back from each one
To see how this plays out, follow a $60,000 kitchen renovation in Ontario, paid in four equal draws as work is supplied. The contract builds the holdback into the payment schedule from day one. No certificate of substantial performance is published, because this is a household job. To keep the arithmetic clean, the figures leave HST out.
By the time the last cabinet door is hung, you've paid $54,000 and quietly kept $6,000 in reserve. Each invoice also opens a short window worth knowing about. Since January 1, 2026, an Ontario invoice is deemed "proper" unless you point out its deficiencies in writing within 7 days. If a draw invoice is missing information you need, say so that week.
The calendar after the last nail
Once the fourth draw's work is done on Friday, November 27, 2026, the contract is complete and the 60-day clock starts. Here's how the weeks unfold:
- Friday, November 27, 2026 (day 0): The contract is completed and the lien window opens.
- Monday, January 11, 2027 (day 45): In our example, this is when trouble arrives (see below).
- Tuesday, January 26, 2027 (day 60): The 60-day preservation window closes.
- Wednesday, January 27, 2027: You run a title search to confirm nothing is registered.
- By Tuesday, February 9, 2027: If title is clear, the $6,000 holdback goes to your contractor. The deadline is 14 days after the window closes.
That last date is a real obligation. After the January 2026 amendments, Cassels notes that the owner must pay the remaining holdback to the contractor within 14 days after the lien-preservation period has expired, or after any preserved liens are satisfied, discharged or otherwise provided for. Holding on to it "just in case" past that point isn't an option the statute gives you.
What happens when a supplier registers a lien on day 45
Now for the scenario the holdback exists for. On January 11, 2027, the cabinet supplier registers a $9,000 lien on your home's title because your contractor never paid for the boxes and doors. You had no contract with the supplier, and you paid your contractor every draw on time.
Here's where the $6,000 earns its keep. Under Ontario's Construction Act, your personal liability to valid lien claimants is tied to the holdback you were required to retain. The supplier's claim is $9,000, but the fund you're answerable for is the $6,000 you kept back. You don't release that money to the contractor while the lien sits on title, and this is the moment to call a construction lawyer, before any more money changes hands, so the lien is dealt with through the process the Act sets out.
Now imagine a neighbour who did the same renovation and paid all $60,000 as each invoice arrived. Their liability is still measured by the $6,000 they were supposed to keep back, but that money is already in the contractor's account. To clear the supplier's claim against their home, they may have to find up to $6,000 more out of pocket. It's the same kitchen and the same supplier, and one homeowner pays twice while the other doesn't.
Some homeowners finance a kitchen like this through home equity, and the draw schedule matters there too.
If you're weighing how to fund a renovation, our guide to HELOCs explained covers how draws from a line of credit line up with progress payments.